A dispute over land acquisition that threatened to sink a long-awaited traffic calming scheme and flood relief works in Claregalway has been resolved.

A meeting of the Athenry Oranmore Municipal District councillors heard that an agreement had been reached with the landowner, enabling the Council to proceed with its plans to install a surface water drainage scheme at the bridge.

Cllr Jim Cuddy (Ind) said following repeated representations, he had been assured that a resolution had been found.

“I have been informed that we are waiting for Transport Infrastructure Ireland (TII) to come back to the Council to tell them to proceed,” said Cllr Cuddy.

This came as councillors hit out at the lack of progress on the project, with Cllr James Charity (Ind) pointing out that it had been three years since they approved the project.

“I have had a lot of complains in the last few days about flash flooding in Claregalway, on the street outside Centra . . . we’ve mentioned it in here ad nauseum,” he said.

“It is very frustrating for communities and residents up there that this is not progressing – it’s a long-standing problem that’s being put on the long finger.”

Cllr Albert Dolan (FF) said it was disappointing that having approved the project in 2019, councillors were being kept in the dark and had received no official communication from the National Roads Project Office (NRPO) to explain the delay.

“It’s three years on and we have not seen any progress . . . the Athenry Oranmore councillors are not happy that this has been delayed for so long without being given a reason,” said Cllr Dolan.

Cllr Charity suggested that a representative of the NRPO should be invited to a meeting of local area councillors to explain the lack of progress.

“If the matter is progressing, we need an update from them. Resolution with the landowner is one thing but the TII committed to this in 2019, so now there is a question of funding as well,” said Cllr Charity.

Cllr Liam Carroll (FG) concurred and said with the increasing cost of construction materials, funding would need to be addressed without delay.