Galway County Council acts over stone crushing works


GALWAY County Council has issued an enforcement notice in relation to land clearance, access tracks and pathways, as well as unauthorised stone crushing, at a site in North Galway, potentially connected to a major solar farm project in that area.
The enforcement notice [EN25/202] was issued to Kings Valley Farm Ltd, Galway Technology Park, Galway, and two of the company's directors, as well as one other named individual, by the Council, under Section 154 of the Planning and Development Act, 2,000, on March 16.
In their official enforcement notice, the Council state that the Planning Authority [GCC], 'considers that unauthorised development has been, is being, or may be carried out, by you [the named parties], in the townland of Oakwood South [An Garran Darach Theas]', Abbeyknockmoy.
The notice further states that it relates to 'unauthorised land clearance within the zone of notification of a monument; the unauthorised creation of an access track/pathway; and the unauthorised crushing of stone [all at the same location close to Knockroe Hill].
Under the terms of the Enforcement Notice, the Planning Authority requires that the Kings Valley Farm Ltd work, 'being one for which no permission has been granted' - would cease, with six specific requirements.
These include that 'within 24 hours from the date of the service of the notice [c. March 16th, 2026], all land clearance/reclamation works would cease as would the unauthorised crushing of stone.
Kings Valley Farm Ltd has been given a period of two weeks to remove all machinery, including excavators and rollers from the site; to remove the unauthorised newly constructed track/pathway; and to provide evidence to the Planning Authority of engagement with the National Monuments Service [NMS].
The company has been given a four-week timeframe to submit an archaeological report from a suitably qualified archaeologist, including an assessment of the unauthorised works undertaken and their impact on the archaeological heritage of the site.
The Council Notice also warns that, unless the steps specified are not undertaken by Kings Valley Farm Ltd, 'that they may be guilty of an offence'.
The proposed solar farm - possibly covering up to 1,000 acres of land in the Abbeyknockmoy, Monivea and Ballyglunin area - has caused huge divisions in the locality with a community/residents group, opposed to the development, formed over the past year.
AMASS [Abbeyknockmoy and Monivea Against Solar Sprawl] has expressed huge concerns about the impact of the project - and particularly its proposed battery plant - on the local environment, landscape and area.
A spokesperson for AMASS told the Connacht Tribune that they welcomed the issuing of the enforcement order on the site which they said was on part of the proposed solar farm project.
"This is an unauthorised development and it needs to stopped - this is good news for local residents," the spokesperson stated.
Power Capital Renewable Energy [PCRE] are behind the solar farm plan: preliminary land purchase agreements are understood to have been reached with an estimated 20 landowners.